Projects Currently Underway

Cleveland Street Reconstruction Project


This project was awarded to All American Concrete of West Liberty, Iowa, on July 20, 2017, in the amount of $403,889.10.  The project will begin Monday, Aug. 14, 2017, and consists of removing and replacing existing concrete on Cleveland Street from Park Avenue to 2nd Avenue. There will be access provided to businesses at all times. However, there may be some delays. Please be patient. Contract completion date is September 30, 2017. Contact City of Muscatine Public Works at 263-8933 if you have any questions. Pictured below is a guide to the four phases of the project. However, the schedule is not cast in concrete and is contingent upon the requirements of the contractor. The phases may change as needed.

Phases Of Construction


West Hill Sewer Separation Project - Phase 3


Phase 3 project was awarded on April 16, 2015 to Hagerty Earthworks, LLC of Muscatine, Iowa in the amount of $4,988,688.00.  

Update as of August 10, 2017:  

The focus of the contractor is up around 4th Street Park. The contractor is working on the sanitary sewer services on the west side of 4th Street Park at 4th & Broadway and moving toward Cherry Street. The paving contractor poured the concrete on W. 4th St. from Locust to Broadway this week but the street is not open to traffic. Grading for paving is occuring now on Broadway between the #3 and #4 alleys on the east side of the park. Broadway between the #3 and #4 alley will be paved after the sewer work up to Cherry Street is complete. Once the sewer contractor finishes the grading on Broadway and the sewer work up to Cherry they will move down to E. 5th to do their sanitary sewer replacement work between Cedar Street and Iowa Avenue. 


For more information or updated information, call Steve Dalbey at 563-299-2888. 

Background Information:
In 2004 Stanley Consultants Inc. signed a contract with the city to proceed with a study and projects for the West Hill area. On September 5, 2007 the city received a stamped Consent Order from the U.S. Environmental Protection Agency requiring that by December 31, 2010 the city would “submit to EPA and IDNR a report describing the projects needed to complete the separation of the remaining combined portions of the sewer system including the West Hill area”. The report “shall include a schedule and estimated cost for completing each project identified therein, and an update on the city’s plans for financing the projects”. Further, “By DECEMBER 31, 2024, completed all projects described . . . above”. Four projects have been identified, each estimated at $15 million to be implemented over the next 14 years to comply with the December 31, 2024 Consent Order date.


Asphalt Overlay Program 2017


Bids were accepted and a contract was awarded to Illowa Investments, Inc. of Blue Grass, IA on July 20, 2017 in the amount of $519,250.10.    

The list of proposed streets for 2017 follows:
Elfers Street from Grandview Avenue to Dead End
Washington Street from Diagonal Street to River Road
McArthur Street from Lincoln Boulevard to Summit Avenue
Jefferson Street from Lincoln Boulevard to Fillmore Street
Isett Avenue from East 11th Street to Woodlawn Avenue
Cypress Street from East 11th Street to #9 Alley
Howard Street from Clay Street to Jackson Street
Eisenhower Street from Devitt Avenue to Dead End
5th Avenue from Webster Street to Blaine Street
Lincoln Boulevard from Clay Street to Lake Park Boulevard
57th Street from 67th Avenue to rail road tracks 
 

Sidewalk Program 2017

The 2017 Sidewalk program has not been awarded as yet.